FORM 8-K for 20130930 PR and Slides


 
UNITED STATES
SECURITIES AND EXCHANGE COMMISSION
Washington, D.C. 20549

 
FORM 8-K
 
 
CURRENT REPORT
Pursuant to Section 13 or 15(d) of The Securities Exchange Act of 1934

Date of Report (Date of earliest event reported): November 1, 2013

 
 
 
PORTLAND GENERAL ELECTRIC COMPANY
(Exact name of registrant as specified in its charter)
 
 
 
 
 
 
Oregon
001-5532-99
     93-0256820          
(State or other jurisdiction
of incorporation)
(Commission
File Number)
     (I.R.S. Employer          
     Identification No.)          
121 SW Salmon Street, Portland, Oregon 97204
(Address of principal executive offices, including zip code)

Registrant’s telephone number, including area code: (503) 464-8000
 

Check the appropriate box below if the Form 8-K filing is intended to simultaneously satisfy the filing obligation of the registrant under any of the following provisions:

[ ]
Written communications pursuant to Rule 425 under the Securities Act (17 CFR 230.425)

[ ]
Soliciting material pursuant to Rule 14a-12 under the Exchange Act (17 CFR 240.14a-12)

[ ]
Pre-commencement communications pursuant to Rule 14d-2(b) under the Exchange Act (17 CFR 240.14d-2(b))

[ ]
Pre-commencement communications pursuant to Rule 13e-4(c) under the Exchange Act (17 CFR 240.13e-4(c))
 




Item 2.02    Results of Operations and Financial Condition.

The following information is furnished pursuant to both Item 2.02 and Item 7.01.

On November 1, 2013, Portland General Electric Company (the “Company”) issued a press release announcing its financial results for the three and nine month periods ended September 30, 2013. The press release is furnished herewith as Exhibit 99.1 to this Report.

Item 5.02
Departure of Directors or Certain Officers; Election of Directors; Appointment of Certain Officers; Compensatory Arrangements of Certain Officers.

(b) On October 30, 2013, Corbin A. McNeill, Jr., Chairman of the Board of Directors of the Company (the “Board”) notified the Board of his retirement from the Board effective October 31, 2013. Mr. McNeill was a member of the Nominating and Corporate Governance Committee of the Board.

The Board has elected director Jack E. Davis to succeed Mr. McNeill as Chairman of the Board, effective October 31, 2013. Mr. Davis has been a member of the Board since June 2012 and also serves on the Nominating and Corporate Governance Committee. Mr. Davis has extensive regulated utility experience. He served as Chief Executive Officer of Arizona Public Service Company (“APS”), a subsidiary of Pinnacle West Capital Corporation (“Pinnacle West”), from September 2002 until his retirement in March 2008. He also served as President of APS from October 1998 to October 2007 and as a director of APS from October 1998 to May 2008. Mr. Davis served as President and Chief Operating Officer of Pinnacle West from September 2003 to March 2008, and as a director of Pinnacle West from 2001 to 2008. During his 35 years at APS, Mr. Davis held executive and management positions in various areas of the company including commercial operations, generation and transmission, customer service, and power operations.

Item 7.01    Regulation FD Disclosure.

At 11:00 a.m. ET on Friday, November 1, 2013, the Company will hold its quarterly earnings call and webcast, and will utilize a slide presentation in conjunction with the earnings call. A copy of the slide presentation is furnished herewith as Exhibit 99.2.

Item 9.01
Financial Statements and Exhibits.

(d)
 
Exhibits.
99.1
 
Press Release issued by Portland General Electric Company dated November 1, 2013.
99.2
 
Portland General Electric Company Third Quarter 2013 Slides dated November 1, 2013.


2



SIGNATURE

Pursuant to the requirements of the Securities Exchange Act of 1934, the registrant has duly caused this report to be signed on its behalf by the undersigned thereunto duly authorized.

 
 
 
 
PORTLAND GENERAL ELECTRIC COMPANY
 
 
 
 
(Registrant)
 
 
 
 
 
Date:
October 31, 2013
 
By:
/s/ James F. Lobdell
 
 
 
 
James F. Lobdell
 
                                                                             
 
 
Senior Vice President of Finance,
Chief Financial Officer and Treasurer


3
Exhibit 99.1 20130930 Press Release


Exhibit 99.1
Portland General Electric
One World Trade Center
121 S.W. Salmon Street
Portland, Oregon 97204

News Release
 
 
 
FOR IMMEDIATE RELEASE
 
 
Nov. 1, 2013
 
 
 
 
 
Media Contact:
 
Investor Contact:
Steven Corson
 
Bill Valach
Corporate Communications
 
Investor Relations
Phone: 503-464-8444
 
Phone: 503-464-7395

Portland General Electric announces third quarter results

PORTLAND, Ore. — Portland General Electric Company (NYSE: POR) today reported net income of $31 million, or 40 cents per diluted share, for the third quarter of 2013. This compares with net income of $38 million, or 50 cents per diluted share, for the third quarter of 2012. The decrease in earnings is primarily the result of higher power costs due to plant outages and increased delivery system costs due to service restoration work and other planned expenses. The company is reducing its full-year 2013 earnings guidance from $1.25 - $1.40 per share to $1.20 - $1.30 per share.

“While the generating plant outages have been challenging this year, the balance of the company's operations have been very strong,” said Jim Piro, president and chief executive officer. “Our performance in distribution reliability and customer satisfaction is top quartile, we reached a reasonable settlement on all issues in our 2014 general rate case, and the construction of our new thermal and renewable resources is proceeding on time and on budget.”
Company updates

Board of directors update—Effective Oct. 31, Chairman Corbin McNeill has announced his retirement from PGE’s board of directors and Jack Davis has been elected as the new chairman. McNeill joined the board in 2004 and has made significant contributions to PGE during the past decade.
    
“Corbin has provided outstanding leadership, perspective and guidance during his tenure as chairman,” Piro said. “We appreciate his steadfast dedication and service to our customers, employees and shareholders.”

Davis has been a member of the PGE board of directors since June 2012. He has extensive knowledge of the utility industry with over 35 years of utility experience at Arizona Public Service Company, including management positions in generation, transmission, power operations and customer service, and six years as chief executive officer.

Generation projects—PGE is making progress on its three new generation projects. Construction is underway on Port Westward Unit 2, a 220 megawatt natural gas-fired capacity resource and on Tucannon River, a 267 MW wind farm. Engineering and design is underway for the Carty Generating Station, a 440 MW natural gas-fired energy resource, and construction is expected to begin in early 2014.

General rate case—PGE filed a 2014 general rate case in February and has settled all items with the Oregon Public Utility Commission staff and interveners. Stipulating parties have settled on an allowed return on equity of 9.75 percent and an average rate base of $3.1 billion. The stipulated items, including a





recent stipulation on pension expense, result in an expected increase of $67 million in annual revenue requirements. The company will provide a final update on power costs in November and awaits a final order from the OPUC in December.

Generation plant outages— The Boardman and Colstrip coal-fired plants both tripped off-line on July 1st due to equipment failures. Boardman came back online at the end of July and Colstrip is expected to come back online in the first quarter of 2014. Coyote Springs, one of PGE’s natural gas-fired plants, tripped off-line in late August due to cracks in the steam turbine rotor. Repairs to the plant are underway and Coyote Springs is expected to be online later this month. PGE’s share of repair costs for the coal plants - approximately $13 million - is expected to be covered by insurance, net of approximately $2 million in deductibles. Repair costs for Coyote Springs are estimated to be $2 million. All together, replacement power costs in 2013 for the three outages are expected to be $16 to $18 million.

Transmission discussions with the Bonneville Power Administration— In late October, PGE and BPA agreed to discontinue discussions regarding PGE’s potential ownership of approximately 1,500 MW of BPA’s transmission capacity rights. PGE and BPA concluded that they would not be able to reach an agreement on financial terms that benefited both PGE and BPA customers. At this time, PGE has determined that transmission service offered under BPA’s open access transmission tariff is the best option for meeting its current transmission needs.

Third quarter operating results

Total revenues decreased $15 million, or 3 percent, to $435 million in the third quarter of 2013 from $450 million in the third quarter of 2012 primarily due to the net effect of the following:

An $11 million decrease resulting from lower average prices due primarily to the reduction in power costs as forecasted in the company’s 2013 annual power cost update tariff and a slightly larger portion of energy deliveries going to customers who purchase their energy from electricity service suppliers;

A $7 million decrease related to the company’s power cost adjustment mechanism, as the estimated refund to customers related to the 2011 PCAM was reduced in the third quarter of 2012 as a result of the application of the regulated earnings test, with no estimated refund to or collection from customers recorded in the third quarter of 2013; and

A $3 million decrease related to the decoupling mechanism, with a $1 million potential refund recorded in the third quarter of 2013 compared with a $2 million potential collection recorded in the third quarter of 2012; partially offset by

$3 million, or 16 percent, increase in wholesale revenues consisting of a 57 percent increase in the average price of wholesale power and a 25 percent decrease in the volume sold; and

A $2 million increase related to a 1 percent increase in the volume of retail energy delivered primarily due to the effects of weather. Residential energy deliveries were up 2 percent, while commercial and industrial deliveries were comparable to the third quarter of 2012.

Purchased power and fuel expense increased $8 million, or 4 percent, for the third quarter of 2013 compared to the third quarter of 2012. The increase consisted of $15 million related to a 9 percent increase in the average variable power cost, which is largely due to the unplanned plant outages, partially offset by $7 million related to a 4 percent decrease in total system load. During the third quarter of 2013, the company incurred approximately $11 million of incremental replacement power costs related to the unplanned plant outages.






Production and distribution expense increased $5 million, or 10 percent, in the third quarter of 2013 compared with the third quarter of 2012, primarily due to planned higher operating and maintenance costs related to the company’s distribution system, including technology upgrades as well as increased repair and restoration work.

Interest expense decreased $2 million, or 7 percent, in the third quarter of 2013 compared with the third quarter of 2012, due to an increase in the allowance for debt funds used for construction driven by a higher average construction work-in-progress balance resulting from the commencement of the construction of Port Westward Unit 2, Carty Generating Station and Tucannon River Wind Farm in 2013, as well as a decrease in interest expense driven by the timing of the maturities and issuances of long-term debt.

Other income, net increased $6 million in the third quarter of 2013 compared with the third quarter of 2012, primarily due to higher earnings on the non-qualified benefit plan trust assets, as well as an increase in the allowance for equity funds used for construction from the higher average CWIP balance.

Income tax expense was $4 million in the third quarter of 2013 compared with $19 million in the third quarter of 2012. The decrease is primarily due to the decrease in the annual estimated pre-tax income for 2013 compared to 2012, which was driven by the $52 million expense for Cascade Crossing and a $9 million industrial customer refund both recorded in the second quarter of 2013.

2013 earnings guidance

PGE is reducing full-year 2013 earnings guidance from $1.25 to $1.40 per share to $1.20 to $1.30 per share primarily due to replacement power costs for the Coyote Springs outage. This guidance range is based on:

Weather-adjusted energy deliveries comparable to weather-adjusted 2012;
Normal hydro conditions and wind conditions in line with expectations;
Incremental replacement power costs of $16 million to $18 million for the three plant outages;
Ongoing operating and maintenance costs between $440 million and $460 million;
Depreciation expense between $240 million and $250 million; and
Capital expenditures between $710 million and $730 million.

Excluding the impacts of the Cascade Crossing charge and the customer billing matter, PGE’s adjusted operating earnings guidance for 2013 would be $1.70 to $1.80 per share, as shown below:
2013 GAAP earnings per share guidance
$ 1.20 - 1.30
Exclude the second quarter Cascade Crossing expense
0.42
Exclude the second quarter customer billing matter revenue reduction
0.07
2013 Non-GAAP adjusted operating earnings per share guidance
$ 1.70 - 1.80

PGE believes this non-GAAP adjusted guidance is useful to investors, analysts, rating agencies and other parties, as it facilitates the analysis of our results of operations from one period to another and provides clarity concerning the impact of certain events on operational results.

Third quarter 2013 earnings call and web cast — Nov. 1, 2013

PGE will host a conference call with financial analysts and investors on Fri. Nov. 1, at 11 a.m. ET. The conference call will be web cast live on the PGE website at portlandgeneral.com. A replay of the call will be available beginning at 1 p.m. ET on Friday, Nov. 1 through Friday, Nov. 8.

Jim Piro, president and CEO; Jim Lobdell, senior vice president of finance, CFO, and treasurer; and Bill Valach, director, investor relations, will participate in the call. Management will respond to questions following formal comments.






The attached unaudited condensed consolidated statements of income, condensed consolidated balance sheets, and condensed consolidated statements of cash flows, as well as the supplemental operating statistics, are an integral part of this earnings release.

# # # # #

About Portland General Electric Company

Portland General Electric Company is a vertically integrated electric utility that serves approximately 836,000 residential, commercial and industrial customers in the Portland/Salem metropolitan area of Oregon. The company’s headquarters are located at 121 S.W. Salmon Street, Portland, Oregon 97204. Visit PGE’s website at portlandgeneral.com.

Safe Harbor Statement
Statements in this news release that relate to future plans, objectives, expectations, performance, events and the like may constitute “forward-looking statements” within the meaning of the Private Securities Litigation Reform Act of 1995, Section 27A of the Securities Act of 1933, as amended, and Section 21E of the Securities Exchange Act of 1934, as amended. Forward-looking statements include statements regarding earnings guidance; statements regarding future load, hydro conditions and operating and maintenance costs; statements concerning implementation of the company’s integrated resource plan; statements concerning future compliance with regulations limiting emissions from generation facilities and the costs to achieve such compliance; as well as other statements containing words such as “anticipates,” “believes,” “intends,” “estimates,” “promises,” “expects,” “should,” “conditioned upon,” and similar expressions. Investors are cautioned that any such forward-looking statements are subject to risks and uncertainties, including reductions in demand for electricity and the sale of excess energy during periods of low wholesale market prices; operational risks relating to the company’s generation facilities, including hydro conditions, wind conditions, disruption of fuel supply, and unscheduled plant outages, which may result in unanticipated operating, maintenance and repair costs, as well as replacement power costs; the costs of compliance with environmental laws and regulations, including those that govern emissions from thermal power plants; changes in weather, hydroelectric and energy markets conditions, which could affect the availability and cost of purchased power and fuel; changes in capital market conditions, which could affect the availability and cost of capital and result in delay or cancellation of capital projects; failure to complete capital projects on schedule or within budget, or the abandonment of capital projects, which could result in the company’s inability to recover project costs; the outcome of various legal and regulatory proceedings; and general economic and financial market conditions. As a result, actual results may differ materially from those projected in the forward-looking statements. All forward-looking statements included in this news release are based on information available to the company on the date hereof and such statements speak only as of the date hereof. The company assumes no obligation to update any such forward-looking statement. Prospective investors should also review the risks and uncertainties listed in the company’s most recent annual report on form 10-K and the company’s reports on forms 8-K and 10-Q filed with the United States Securities and Exchange Commission, including management’s discussion and analysis of financial condition and results of operations and the risks described therein from time to time.
POR-F
Source: Portland General Electric Company





PORTLAND GENERAL ELECTRIC COMPANY AND SUBSIDIARIES
CONDENSED CONSOLIDATED STATEMENTS OF INCOME
(In millions, except per share amounts)
(Unaudited)

 
Three Months Ended
 
Nine Months Ended
 
September 30,
 
September 30,
 
2013
 
2012
 
2013
 
2012
Revenues, net
$
435

 
$
450

 
$
1,311

 
$
1,342

Operating expenses:
 
 
 
 
 
 
 
Purchased power and fuel
190

 
182

 
538

 
533

Production and distribution
54

 
49

 
169

 
153

Cascade Crossing transmission project

 

 
52

 

Administrative and other
49

 
50

 
158

 
160

Depreciation and amortization
62

 
63

 
186

 
188

Taxes other than income taxes
27

 
24

 
79

 
77

Total operating expenses
382

 
368

 
1,182

 
1,111

Income from operations
53

 
82

 
129

 
231

Interest expense
25

 
27

 
75

 
82

Other income:
 
 
 
 
 
 
 
Allowance for equity funds used during construction
4

 
1

 
8

 
4

Miscellaneous income, net
3

 

 
5

 
2

Total other income
7

 
1

 
13

 
6

Income before income tax expense
35

 
56

 
67

 
155

Income tax expense
4

 
19

 
10

 
43

Net income
31

 
37

 
57

 
112

Less: net loss attributable to noncontrolling interests

 
(1
)
 
(1
)
 
(1
)
Net income attributable to Portland General Electric Company
$
31

 
$
38

 
$
58

 
$
113

 
 
 
 
 
 
 
 
Weighted-average shares outstanding (in thousands):
 
 
 
 
 
 
 
Basic
77,637

 
75,528

 
76,401

 
75,486

Diluted
78,330

 
75,541

 
76,703

 
75,500

Earnings per share—basic and diluted
$
0.40

 
$
0.50

 
$
0.76

 
$
1.49

Dividends declared per common share
$
0.275

 
$
0.270

 
$
0.820

 
$
0.805








PORTLAND GENERAL ELECTRIC COMPANY AND SUBSIDIARIES
CONDENSED CONSOLIDATED BALANCE SHEETS
(In millions)
(Unaudited)
 
 
September 30,
 
December 31,
 
2013
 
2012
ASSETS
 
 
 
Current assets:
 
 
 
Cash and cash equivalents
$
91

 
$
12

Accounts receivable, net
137

 
152

Unbilled revenues
67

 
97

Inventories
72

 
78

Margin deposits
36

 
46

Regulatory assets—current
99

 
144

Other current assets
63

 
93

Total current assets
565

 
622

Electric utility plant, net
4,659

 
4,392

Regulatory assets—noncurrent
504

 
524

Nuclear decommissioning trust
82

 
38

Non-qualified benefit plan trust
34

 
32

Other noncurrent assets
47

 
62

Total assets
$
5,891

 
$
5,670

 
 
 
 
LIABILITIES AND EQUITY
 
 
 
Current liabilities:
 
 
 
Accounts payable
$
99

 
$
98

Liabilities from price risk management activities - current
89

 
127

Short-term debt

 
17

Current portion of long-term debt

 
100

Accrued expenses and other current liabilities
192

 
179

Total current liabilities
380

 
521

Long-term debt, net of current portion
1,761

 
1,536

Regulatory liabilities—noncurrent
852

 
765

Deferred income taxes
565

 
588

Unfunded status of pension and postretirement plans
253

 
247

Non-qualified benefit plan liabilities
103

 
102

Asset retirement obligations
96

 
94

Liabilities from price risk management activities—noncurrent
71

 
73

Other noncurrent liabilities
17

 
14

Total liabilities
4,098

 
3,940

Total equity
1,793

 
1,730

Total liabilities and equity
$
5,891

 
$
5,670









PORTLAND GENERAL ELECTRIC COMPANY AND SUBSIDIARIES
CONDENSED CONSOLIDATED STATEMENTS OF CASH FLOWS
(In millions)
(Unaudited)

 
Nine Months Ended
September 30,
 
2013
 
2012
Cash flows from operating activities:
 
 
 
Net income
$
57

 
$
112

Depreciation and amortization
186

 
188

Capitalized costs expensed related to Cascade Crossing
52

 

Other non-cash income and expenses, net included in Net income
40

 
99

Changes in working capital
94

 
57

Proceeds received from legal settlement
44

 

Other, net
(14
)
 
(6
)
Net cash provided by operating activities
459

 
450

Cash flows from investing activities:
 
 
 
Capital expenditures
(453
)
 
(218
)
Contribution to Nuclear decommissioning trust
(44
)
 

Sale of solar power facility

 
10

Other, net
6

 
(1
)
Net cash used in investing activities
(491
)
 
(209
)
Cash flows from financing activities:
 
 
 
Net issuance of long-term debt
123

 

Proceeds from issuance of common stock, net of issuance costs
67

 

Maturities of commercial paper, net
(17
)
 
(30
)
Dividends paid
(62
)
 
(61
)
Net cash provided by (used in) financing activities
111

 
(91
)
Increase in cash and cash equivalents
79

 
150

Cash and cash equivalents, beginning of period
12

 
6

Cash and cash equivalents, end of period
$
91

 
$
156

 
 
 
 







PORTLAND GENERAL ELECTRIC COMPANY AND SUBSIDIARIES
SUPPLEMENTAL OPERATING STATISTICS
(Unaudited)

 
Three Months Ended
 
Nine Months Ended
 
September 30,
 
September 30,
 
2013
 
2012
 
2013
 
2012
Revenues (dollars in millions):
 
 
 
 
 
 
 
Retail:
 
 
 
 
 
 
 
Residential
$
186

 
$
187

 
$
611

 
$
630

Commercial
162

 
168

 
461

 
476

Industrial
55

 
57

 
160

 
166

Subtotal
403

 
412

 
1,232

 
1,272

Other retail revenues, net

 
10

 
(6
)
 
6

Total retail revenues
403

 
422

 
1,226

 
1,278

Wholesale revenues
22

 
19

 
59

 
38

Other operating revenues
10

 
9

 
26

 
26

Total revenues
$
435

 
$
450

 
$
1,311

 
$
1,342

 
 
 
 
 
 
 
 
Energy sold and delivered (MWh in thousands):
 
 
 
 
 
 
 
Retail energy sales:
 
 
 
 
 
 
 
Residential
1,660

 
1,626

 
5,469

 
5,506

Commercial
1,811

 
1,848

 
5,132

 
5,239

Industrial
823

 
886

 
2,378

 
2,573

Total retail energy sales
4,294

 
4,360

 
12,979

 
13,318

Retail energy deliveries:
 
 
 
 
 
 
 
Commercial
146

 
115

 
408

 
327

Industrial
275

 
210

 
808

 
607

Total retail energy deliveries
421

 
325

 
1,216

 
934

Total retail energy sales and deliveries
4,715

 
4,685

 
14,195

 
14,252

Wholesale energy deliveries
581

 
771

 
1,892

 
1,861

Total energy sold and delivered
5,296

 
5,456

 
16,087

 
16,113

 
 
 
 
 
 
 
 
Number of retail customers at end of period:
 
 
 
 
 
 
 
Residential
 
 
 
 
729,512

 
723,804

Commercial
 
 
 
 
105,315

 
104,749

Industrial
 
 
 
 
202

 
216

Direct access
 
 
 
 
511

 
511

Total retail customers
 
 
 
 
835,540

 
829,280









PORTLAND GENERAL ELECTRIC COMPANY AND SUBSIDIARIES
SUPPLEMENTAL OPERATING STATISTICS, continued
(Unaudited)

 
Three Months Ended
 
Nine Months Ended
 
September 30,
 
September 30,
 
2013
 
2012
 
2013
 
2012
Sources of energy (MWh in thousands):
 
 
 
 
 
 
 
Generation:
 
 
 
 
 
 
 
Thermal:
 
 
 
 
 
 
 
Coal
830

 
995

 
2,985

 
2,280

Natural gas
1,096

 
856

 
2,300

 
1,993

Total thermal
1,926

 
1,851

 
5,285

 
4,273

Hydro
314

 
331

 
1,231

 
1,461

Wind
372

 
341

 
1,001

 
964

Total generation
2,612

 
2,523

 
7,517

 
6,698

Purchased power:
 
 
 
 
 
 
 
Term
940

 
1,895

 
4,821

 
6,042

Hydro
385

 
422

 
1,286

 
1,358

Wind
92

 
95

 
269

 
272

Spot
1,147

 
460

 
1,850

 
1,641

Total purchased power
2,564

 
2,872

 
8,226

 
9,313

Total system load
5,176

 
5,395

 
15,743

 
16,011

Less: wholesale sales
(581
)
 
(771
)
 
(1,892
)
 
(1,861
)
Retail load requirement
4,595

 
4,624

 
13,851

 
14,150


 
Heating Degree-days
 
Cooling Degree-days
 
2013
 
2012
 
2013
 
2012
First quarter
1,902

 
1,967

 

 

Average
1,850

 
1,848

 

 

Second quarter
593

 
709

 
82

 
40

Average
721

 
714

 
68

 
68

Third quarter
90

 
58

 
457

 
395

Average
82

 
81

 
385

 
387

Year-to-date
2,585

 
2,734

 
539

 
435

Year-to-date average
2,653

 
2,643

 
453

 
455

* — “Average” amounts represent the 15-year rolling averages provided by the National Weather Service (Portland Airport).




porq3earningscallslidesv
Earnings Conference Call Third Quarter 2013 1 Exhibit 99.2


 
Cautionary Statement 2 Information Current as of November 1, 2013 Except as expressly noted, the information in this presentation is current as of November 1, 2013 — the date on which PGE filed its Quarterly Report on Form 10-Q for the quarter ended September 30, 2013 — and should not be relied upon as being current as of any subsequent date. PGE undertakes no duty to update the presentation, except as may be required by law. Forward-Looking Statements Statements in this presentation that relate to future plans, objectives, expectations, performance, events and the like may constitute “forward-looking statements” within the meaning of the Private Securities Litigation Reform Act of 1995, Section 27A of the Securities Act of 1933, as amended, and Section 21E of the Securities Exchange Act of 1934, as amended. Forward-looking statements include statements regarding earnings guidance, statements regarding future load, hydro conditions and operating and maintenance costs; statements concerning implementation of the Company’s Integrated Resource Plan and related future capital expenditures, statements concerning future compliance with regulations limiting emissions from generation facilities and the costs to achieve such compliance; statements regarding the outcome of any legal or regulatory proceeding; as well as other statements containing words such as “anticipates,” “believes,” “intends,” “estimates,” “promises,” “expects,” “should,” “conditioned upon,” and similar expressions. Investors are cautioned that any such forward-looking statements are subject to risks and uncertainties, including the reductions in demand for electricity and the sale of excess energy during periods of low wholesale market prices; operational risks relating to the Company’s generation facilities, including hydro conditions, wind conditions, disruption of fuel supply, and unscheduled plant outages, which may result in unanticipated operating, maintenance and repair costs, as well as replacement power costs; the costs of compliance with environmental laws and regulations, including those that govern emissions from thermal power plants; changes in weather, hydroelectric and energy markets conditions, which could affect the availability and cost of purchased power and fuel; changes in capital market conditions, which could affect the availability and cost of capital and result in delay or cancellation of capital projects; failure to complete projects on schedule and within budget, or the abandonment of capital projects, which could result in the Company’s inability to recover project costs; the outcome of various legal and regulatory proceedings; and general economic and financial market conditions. As a result, actual results may differ materially from those projected in the forward-looking statements. All forward-looking statements included in this presentation are based on information available to the Company on the date hereof and such statements speak only as of the date hereof. The Company assumes no obligation to update any such forward-looking statement. Prospective investors should also review the risks and uncertainties listed in the Company’s most recent Annual Report on Form 10-K and the Company’s reports on Forms 8-K and 10-Q filed with the United States Securities and Exchange Commission, including Management’s Discussion and Analysis of Financial Condition and Results of Operations and the risks described therein from time to time.


 
Leadership Presenting Today 3 Jim Lobdell Senior Vice President of Finance, CFO & Treasurer Jim Piro President & CEO


 
On Today’s Call 4  Growth Initiatives  Regulatory Update  Operational Update  Economy and Customers  Financial Update  2013 Outlook


 
Q3 2013 Earnings Results Q1 $0.65 Q1 $0.65 Q2 $0.34 Q2 ($0.29) Q3 $0.50 Q3 $0.40 Q4 $0.38 2012 EPS 2013E EPS 5 NI in millions Q3 2012 Q3 2013 2012 Actuals 2013 Guidance Net Income $38 $31 $141 $93 - $100 EPS $0.50 $0.40 $1.87 $1.20 - $1.30 $1.87 $1.20-$1.30


 
Flexible Capacity Seasonal Capacity Project Name Port Westward Unit 2 Purchased Power Agreements with Iberdrola Project Location Clatskanie, OR 100 MW of winter capacity 100 MW of summer capacity Project Type PGE’s Benchmark Bid Capacity Fuel Technology 220 MW Natural Gas Wärtsilä Reciprocating Engines 12 18-MW units Estimated Capital Cost (excluding AFDC) $300 million Estimated In-Service Date Q1 2015 EPC / Supplier Contractor(s) Black & Veatch / Harder Mechanical & Wärtsilä Regulatory Recovery Method 2015 Test Year General Rate Case Potential Customer Price Impact 3-4% Strategic Initiatives: Capacity Resources 6 $165 $125 $10 2013 2014 2015 PW2 CapEx (in millions)


 
Strategic Initiatives: Renewable Resources 7 $110 $375 $15 2013 2014 2015 Tucannon River CapEx (in millions) Renewable Energy Project Name Tucannon River Wind Farm Project Location Columbia County, WA Project Type EPC Contract on Third Party Site Capacity Fuel Technology 267 MW Wind Project Siemens Turbines Estimated Capital Cost (excluding AFDC) $500 million Estimated In-Service Date First half of 2015 EPC / Supplier Contractor(s) Renewable Energy Service (RES) / Siemens Regulatory Recovery Method Renewable Adjustment Clause Filing/GRC Potential Customer Price Impact 3-4%


 
Strategic Initiatives: Baseload Resources 8 $125 $170 $110 $45 2013 2014 2015 2016 Carty CapEx (in millions) Baseload Energy Project Name Carty Generating Station Project Location Boardman, OR Project Type EPC Contract on Benchmark Site Capacity Fuel Technology 440 MW Natural Gas Mitsubishi CCGT Estimated Capital Cost (excluding AFDC) $450 million Estimated In-Service Date Mid-2016 EPC / Supplier Contractor(s) Abener Construction / Mitsubishi, Sargent & Lundy Regulatory Recovery Method 2016/2017 Test Year General Rate Case Potential Customer Price Impact 6-7%


 
Expected Rate Base and Capital Expenditures 9 $1.4B of Expected Increase in Rate Base (in millions) 2013 2014 2015 2016 2017 TOTAL Base Capital Spending(1) $320 $365 $315 $270 $245 $1,515 Port Westward Unit 2 $165 $125 $10 $300 Tucannon River Wind Farm $110 $375 $15 $500 Carty Generating Station $125 $170 $110 $45 $450 TOTAL $720 $1,035 $450 $315 $245 $2,765 (1) Includes ongoing capex and hydro relicensing as disclosed in the Q3 2013 Form 10-Q filed on November 1, 2013 Note: Amounts exclude AFDC debt and equity $3.1B $4.5B 2012 20172012 2017 8% CAGR Expected Capital Expenditures


 
General Rate Case: 2014 Test Year  All issues settled with OPUC Staff and interveners  Stipulation filed July 10, 2013:  Return on Equity (ROE): 9.75%  Capital Structure: 50% debt, 50% equity  Rate base: $3.1 billion  Stipulation filed September 23, 2013  Pension expense recovery of $19.5 million in 2014  New customer prices effective January 1, 2014 10 in millions Original Filing Request $105 UE 262 Non-Power Cost Stipulation $(42) Load Forecast Update (Revenue) $ 15 UE 266 Power Cost Update $(11) Revised revenue requirement increase $67


 
Operational Update – Plant Outages 11 in millions, PGE Share Boardman Colstrip Unit 4 Coyote Springs Date of Outage July 1 July 1 August 24 Actual/Expected Online Date July 31 Q1 2014 November 2013 Replacement Power Costs $4 $5-$6 $7-8


 
Economic Outlook & Customer Satisfaction 12 Growth in Operating Area  Growth in PGE work order requests  Unemployment rate of 6.8% in core operating area  Employment growth in healthcare, hotels, and restaurants  Manufacturing and high tech industries continue to expand  Load growth forecast of approximately 1% in 2014 GRC


 
Third Quarter Financial Results Quarter over Quarter Drivers of Results 13 NI in millions Q3 2012 Q3 2013 Net Income $38 $31 EPS $0.50 $0.40 in millions, pre-tax Q3 over Q3 Increased purchased power and fuel $(8) Delivery system expense $(5) 2011 PCAM refund reduction in Q3 2012 $(7) Increased AFDC + TOLI gains $ 6


 
Total Revenues and Power Costs in millions Q3 2012 Q3 2013 YTD 2012 YTD 2013 Total Revenues $450 $435 $1,342 $1,311 Power Costs $182 $190 $533 $538 18% 16% 14% 9% 43% Q3 2012 Sources of Power Coal Natural Gas Hydro Wind Purchased Power 16% 21% 14% 9% 40% Q3 2013 Sources of Power 14


 
Operating Expenses 15 Interest Expense $27 $25 $82 $75 in millions Q3 2012 Q3 2013 YTD 2012 YTD 2013 Production & Distribution $49 $54 $153 $169 Administrative & General $50 $49 $160 $158 Total O&M $99 $103 $313 $327 Cascade Crossing Expense -- -- -- $52 Depreciation & Amortization $63 $62 $188 $186 Income Tax Expense $19 $4 $43 $10


 
Liquidity and Financing Senior Secured Senior Unsecured Outlook S&P A- BBB Stable Moody’s A2 Baa1 Stable Credit Ratings Total Liquidity as of 9/30/13 (in millions) Credit Facilities $752 Commercial Paper -- Letters of Credit $(56) Cash $91 Available $787 16 $69 $108 $68 $152 $81 $193 $85 2012 2013E Q4 Q3 Q2 Q1 Capital Expenditures (in millions) $710-$730 $303


 
2013 Earnings Guidance Progression 17 2/24/13 Original 2013 Earnings Guidance $1.85 - $2.00 5/1/13 Q1 2013 Earnings Call no change 6/3/13 Cascade Crossing project suspension Customer billing refund $(0.42) $(0.07) Guidance Revised Downward $1.35 - $1.50 8/2/13 Replacement power costs for coal plant outages $(0.10) Guidance Revised Downward $1.25 - $1.40 11/1/13 Replacement power costs for Coyote Springs $(0.05) 2013 Actual Guidance Revised Downward $1.20 - $1.30 11/1/13 Add back Cascade Crossing and customer billing impacts $0.49 2013 Adjusted Operating EPS Guidance $1.70 - $1.80 2013 Actual EPS Guidance: $1.20 - $1.30 per diluted share


 
18 2013 Earnings Guidance Assumptions 2013 EPS Guidance: $1.20 - $1.30 per share  Weather-adjusted energy deliveries comparable to weather-adjusted 2012  O&M expense between $440 and $460 million  D&A expense between $240 and $250 million Assumptions for FY 2013  Capital expenditures between $710 and $730 million  Estimated replacement power costs of $16 - $18 million for plant outages